SEMI CUSTOM HOMETIMELINE

1    FIND A LOT, SELECT DESIGN, AND PERMIT (0 - 6 MONTHS)

​

  • Blueprints and permits are typically completed for you before purchase.

  • If blueprints have not yet been started, you may select a floor plan within Lukaven’s portfolio or our architect’s portfolio. 

  • If not started, blueprints will take 3-5 months, with another 2-3 months for permitting.

  • Lukaven will own the property during construction. 

​

2    REVIEW ALLOWANCE AND SPECIFICATIONS (1 WEEK)

 

  • Allowances are provided rather than options for finishes, allowing you free reign on how the home is finished out.

  • Specifications are provided to cover selections that are difficult to conceptualize if an allowance is provided.

  • Specifications cover the building standards we stand by.

​

3    SIGN CONTRACT (1 DAY)

 

  • A non-refundable 10% deposit is required at signing.

  • Contracts may be signed electronically or in person.

  • Lukaven will fund the project, with the remainder of the payment due at closing.

​

4    BUILD YOUR HOME (9 - 12 MONTHS)

 

  • You’ll receive an invitation to our project intake form, which tracks all details of the project, including budgets.

  • Our team will provide deadlines for all selections for your convenience.

  • You’ll meet our team on site every 2-3 weeks for progress updates.

  • Complete a final walk through to identify all remaining items before moving in.

​

5    MOVE INTO YOUR NEW HOME! (1 Week)

 

  • Receive your turn over package with all warranties and other documentation.

  • Our team can recommend movers and other services required for move in.