SEMI CUSTOM HOMETIMELINE
1 FIND A LOT, SELECT DESIGN, AND PERMIT (0 - 6 MONTHS)
​
-
Blueprints and permits are typically completed for you before purchase.
-
If blueprints have not yet been started, you may select a floor plan within Lukaven’s portfolio or our architect’s portfolio.
-
If not started, blueprints will take 3-5 months, with another 2-3 months for permitting.
-
Lukaven will own the property during construction.
​
2 REVIEW ALLOWANCE AND SPECIFICATIONS (1 WEEK)
-
Allowances are provided rather than options for finishes, allowing you free reign on how the home is finished out.
-
Specifications are provided to cover selections that are difficult to conceptualize if an allowance is provided.
-
Specifications cover the building standards we stand by.
​
3 SIGN CONTRACT (1 DAY)
-
A non-refundable 10% deposit is required at signing.
-
Contracts may be signed electronically or in person.
-
Lukaven will fund the project, with the remainder of the payment due at closing.
​
4 BUILD YOUR HOME (9 - 12 MONTHS)
-
You’ll receive an invitation to our project intake form, which tracks all details of the project, including budgets.
-
Our team will provide deadlines for all selections for your convenience.
-
You’ll meet our team on site every 2-3 weeks for progress updates.
-
Complete a final walk through to identify all remaining items before moving in.
​
5 MOVE INTO YOUR NEW HOME! (1 Week)
-
Receive your turn over package with all warranties and other documentation.
-
Our team can recommend movers and other services required for move in.